Check the floor at the toilet and shower first, patch it with ply of the right thickness and bond class, then size the fan cable before the ceiling goes back up.

Published10 November 2026
Sources6 cited

An RV bathroom is the one room built to get wet. The toilet, the shower and the basin all put water on purpose into a box made of thin ply and staples. So the renovation starts with the same question as the rest of the vehicle, asked more sharply: where has the water been going?

Fixtures and finishes come last. The floor, the cable in the ceiling and the fan come first, because each one ends up buried under the parts you can see.

Start at the floor, around the toilet and the shower

A small leak at the toilet or the shower pan can drip into the subfloor for a long time before it shows. Walk the bathroom floor slowly and press with your heel at the base of the toilet, along the front edge of the shower pan and in the corners. Soft, springy or spongy means rot, and rot here is usually worse underneath than it looks from above.

If the floor is sound, carry on. If it is not, the toilet comes out and the floor gets cut back to solid wood. The guide to where to start on a camper renovation covers finding the source before you repair the damage, which matters more in a bathroom than anywhere else. A patched floor over a leak that is still going is a floor you will patch again.

Taking the toilet out and putting it back

The toilet sits on a floor flange that connects to the black tank below. The seal between them is what keeps the floor dry, and it is a part you replace, not reuse.

Dometic’s instructions for its SeaLand 110 say to “discard old floor seal and mounting bolts”, and that the old floor flange can be reused only if it is in good condition and its fastener holes line up with the new toilet. Its 3210 instructions, for fitting that toilet over an older two-bolt flange, are blunter: “Do not use old hardware or seal.” On that model the toilet fastens through four T-bolts in the flange slots, with the flange gasket over them.

Those are two models from one maker. The details change between toilets, so work from the instructions for the one you are fitting. The principle does not change: new seal, new bolts, flange checked before the toilet goes down, and a flush test for leaks before you call it finished.

Some RV toilets have an electric flush or macerator, and those need a 12 volt feed. Dometic’s 3210 instructions call for 14 gauge stranded copper from the fuse panel through a 2 amp fuse or breaker. Run that cable while the floor and walls are open, not after.

Patching the subfloor: thickness first, then bond class

A floor patch has to finish level with the floor around it. If it sits proud or low, the flange and its seal sit on a step, and the floor covering shows the seam. So measure the old subfloor where it is still sound before you buy anything.

Then buy by the system your supplier actually sells. Imperial and metric ply are different products, not two names for one sheet. These are the measured thicknesses from this site’s own material table, the same data behind the reference tables:

Sold as Actual thickness Sold in Not the same as Difference
3/4 in 18.26 mm US, Canada 18 mm (18.00 mm) 0.26 mm
1/2 in 11.91 mm US, Canada 12 mm (12.00 mm) 0.09 mm
3/8 in 9.13 mm US, Canada 9 mm (9.00 mm) 0.13 mm
18 mm 18.00 mm UK, Europe, Australia, NZ 3/4 in (18.26 mm) 0.26 mm
12 mm 12.00 mm UK, Europe, Australia, NZ 1/2 in (11.91 mm) 0.09 mm
9 mm 9.00 mm UK, Europe, Australia, NZ 3/8 in (9.13 mm) 0.13 mm

Under a floor covering, a fraction of a millimetre is small. In joinery it is not. A 3/4 in panel will not drop into a groove cut for 18 mm ply without being forced, so if the vanity carcass is built with dados or rebates, cut them to the sheet you have, measured, rather than to its label.

Bond class matters more in a bathroom than anywhere else in the vehicle. In North America, APA-stamped panels come in two moisture-resistant bond classifications, Exterior and Exposure 1. According to Building Products Digest’s summary of the APA trademark, Exterior panels have bonds “capable of withstanding repeated wetting and redrying”, while Exposure 1 is for “uses not involving long-term exposure to weather”. A bathroom floor that gets splashed and dried every day is closer to the first description than the second, so I would use Exterior-rated ply for a bathroom patch and for the vanity.

In the UK and Europe the equivalent marking is the EN 314-2 bond class. International Timber describes Class III as “suitable for unprotected exterior use or exposure to frequent wetting”.

Bond class is about the glue, not the wood. The same International Timber page treats bond quality and the timber’s own resistance to fungal decay as separate properties, and notes that some Class III ply only reaches the higher durability rating with preservative treatment. Good glue keeps the layers together. It does not stop the veneers rotting if water sits on them. Seal every face and edge of a bathroom panel, including the backs and the cut edges nobody will see, and keep water from pooling on it in the first place.

The fan is what actually keeps the bathroom dry

Sealing stops water getting into the wood. Ventilation removes the water that is in the air. The US EPA’s home remodelling guidance calls ventilation “especially important in bathrooms to remove unwanted moisture”, says this “helps prevent the growth of mold and mildew”, and says the air should be exhausted directly to the outside. That guidance is written for houses, but the logic carries straight over to a small, closed RV bathroom.

In most RVs the bathroom fan is a 12 volt roof fan, and that puts a cable run in the ceiling. A fan cable that is too thin still spins the fan on the day you test it. It just does so with less voltage than it should, and by the time you notice, the ceiling panel is back up.

How much current to plan for depends on the fan. For one example, an etrailer support answer gives 5 A, or 60 W, for the MaxxFan Deluxe MA00-07500K, and confirms that 5 A is its startup and maximum figure. Check the documentation for the fan you are fitting. The figure below is that example, not a rule.

Here is a 5 A fan worked through our DC wire size calculator on its default settings: 12 V, a 3% voltage drop limit, copper, 77 F (25 C), cable bundled in a loom. Run length is one way, from the fuse panel to the fan.

Run Copper needed AWG to buy Drop Metric to buy Drop
10 ft (3.0 m) 1.48 mm² 14 AWG (2.08 mm²) 2.14% 1.5 mm² 2.97%
15 ft (4.6 m) 2.23 mm² 12 AWG (3.31 mm²) 2.02% 2.5 mm² 2.67%
20 ft (6.1 m) 2.97 mm² 12 AWG (3.31 mm²) 2.69% 4 mm² 2.23%
25 ft (7.6 m) 3.71 mm² 10 AWG (5.26 mm²) 2.12% 4 mm² 2.78%

None of these sizes is limited by heat. The calculator rates even 14 AWG at 12 A when it is bundled in a loom, more than double the fan’s 5 A. What sets the size is voltage drop over the length of the run.

That is the trap. 14 AWG is a common size for small loads, and a 5 A fan on it works. But on the same formula, 14 AWG drops 3.21% at 15 ft, just over the budget, and 4.28% at 20 ft. 16 AWG at 20 ft drops 6.80%. The cable is not overheating. It is simply too long for its size.

Two more things the table shows:

  • The size steps up with length, not load. On the same settings, 14 AWG covers a 5 A fan up to about 14 ft, 12 AWG up to about 22 ft, and past that it is 10 AWG. Measure the run along the path the cable will really take.
  • The two columns are different cable. 12 AWG is 3.31 mm² of copper. The nearest metric cable below it, 2.5 mm², covers the 15 ft run but not the 20 ft one, which needs 4 mm². Buy from whichever column your supplier actually sells, and do not swap between them on a parts list.

The calculator sizes the conductor. It does not choose the fuse, and it assumes one load on the circuit. If the fan shares a circuit with lights or a toilet, add their currents together and size for the total. The methodology page sets out the formula and where it stops, and the 12 V wire size chart covers more loads and lengths.

The order of work in the bathroom

What buries what decides the order.

  1. Find and stop the water. Toilet flange, shower pan, drain fittings, the supply lines and the roof above the fan.
  2. Cut out and patch any soft floor, in ply matched to the old subfloor’s measured thickness and rated for wet use.
  3. Pull every cable and pipe that will sit inside a wall, floor or ceiling. That includes the fan run sized above and any feed to an electric toilet.
  4. Walls, ceiling and floor covering. The flooring guide covers why a floating floor is usually right and where gluing is the exception.
  5. Vanity and cabinets, sealed on every face and edge before they go in. If only the doors are tired, replacing the cabinet doors is a smaller job.
  6. Toilet, taps, shower fittings and trim, with a new flange seal and new bolts, and a leak test before anything is called done.

It is tempting to start at step six, because a new toilet and tap look like progress. In a bathroom, starting there means taking them out again when step one turns out to have been the real job.

Sources

Where this guide states a fact rather than an opinion, it came from one of these. Product names are examples of a category, not endorsements, and nothing here is sponsored.

  1. Remodeling Your Home and Indoor Air Quality, US EPA
  2. The APA Panel Trademark Explained, Building Products Digest
  3. Plywood Standards: Useful Definitions, International Timber
  4. Dometic 3210 toilet installation instructions, page 5, ManualsDir
  5. Dometic SeaLand 110 toilet installation instructions, page 3, ManualsDir
  6. What is Amp/Watt Draw of MaxxFan part # MA00-07500K, etrailer

Illustrations

The diagrams on this page are illustrations, drawn to explain a concept. They are not photographs of a real cabinet and they carry no measurements, because a diagram that looks precise and is not would be worse than no diagram at all. Anything on this site with numbers on it is generated from the underlying data.